Client: KEO Consultants 
Place of performance: Doha, Qatar  
Date and duration: October 2012 – June 2015 
Value of contract: Confidential  

BACKGROUND

Qatar’s Public Works Authority (PWA) awarded the contract for the demolition of the buildings and facilities that were currently on site at the zoo, located opposite Aspire Park and Villagio Mall. These movements were part of a complete overhaul over five years with the plan to convert the zoo into a safari park. 

The first phase of the new Zoo development is scheduled to open for visitors in late 2017 and is expected to be more than seven times the size of the previous 30 year old facility. The Zoo will include 3 hotels and one of the few 7* facilities earmarked for Qatar in coming years. 

In 2013, PWA signed a multi-million dollar contract with an architectural and engineering firm to prepare plans for a new zoo. KEO International Consultants is serving as the projects design and construction supervision consultant.  

It will work with HHCP+PJA, which was hired in December 2012 to prepare the concept Master Plan that includes over 3,000 animals in themed zones. 

PROJECT

Restrata was appointed by KEO International Consultants for the Security Services Commission as part of the overall project plan. Restrata worked closely with HHCP and KEO from the outset of this project to ensure early and costeffective security planning was embedded within the Master Plan Design.   

SOLUTIONS/SERVICES 

We have developed the following series of security reports, guidelines and documents for KEO and Qatar Zoo. 

  • Security Master Plan Review 
  • Security Risk Assessment and Treatment Plan 
  • Security Strategy 
  • Scheme Design  
  • Detailed Design in conjunction with KEO Infrastructure & Design Engineering teams 

Lukoil

Location: Iraq Product: SecureLocate™ IVMS and ITV Services Lukoil is one of the world’s largest international oil and gas companies, with businesses located in over 30 countries worldwide. For their Southern Iraq operations, Lukoil contracted Restrata to provide advanced vehicle tracking, fuel management and monitor driver behaviour. By fitting In-Vehicle Monitoring Systems (IVMS) and Internal […]
Read more

THREE60 Energy

Location: UK Date: December 2020 – Present Restrata was appointed to provide Emergency Response services to THREE60 Energy in order to meet requirements prior to them becoming a Duty Holder Operator for the first time on the UKCS in 2021. THREE60 Energy offers complete asset lifecycle expertise within the offshore energy industry. Restrata provided a robust response […]
Read more

SecureLocate™ IVMS

Aggreko is the world's largest temporary power generation company and a major supplier of temperature control equipment.
Read more

Fill the form to download our brochure




      Request a Demo